Position checked in October 2026: Ofcom’s letter dated 29 January 2026 states that BT plans to retire its PSTN by 31 January 2027. Confirm the migration date and arrangements for each of your services with its provider. This is not a promise that every line changes on the same day.
Use the current plan, not an old headline
The transition from traditional telephone services to internet-based voice has had revised dates. An old reference to a 2025 deadline should not be used to plan a new project. The relevant primary source here is Ofcom’s January 2026 letter on PSTN retirement. Its date is in the document even though the file sits in a directory labelled 2024.
The letter describes BT’s plan and Ofcom’s expectations of communications providers. It is not a service-specific migration notice for your business. Ask your supplier which products you have, what is changing and when action is needed. Do not treat the national planning date as permission to wait until the last week. Complex equipment and number transfers need coordination before the final change.
Inventory more than desk phones
Walk through the premises and identify everything connected to a telephone service. Besides handsets, this may include alarms, lift emergency phones, monitoring equipment, fax and older payment terminals. Ask the organisation responsible for each device how it communicates and whether the proposed replacement service supports it. Do not disconnect or experimentally reconfigure safety equipment without the responsible specialist.
Record the account, line or circuit, associated numbers, connected device and named person responsible. Include services in cupboards, plant rooms and remote sites, not just the reception desk. A bill can help locate lines but may not explain their purpose. Match the records to physical equipment and ask about anything you cannot identify before cancelling a service.
Choose a replacement around the job
A small office may use a hosted voice service, while an organisation with a suitable phone system may investigate SIP connectivity. For an incoming geographic contact, local incoming numbers delivered to a SIP system are one option to examine. That is not a complete migration package: confirm equipment compatibility, outgoing calls, emergency calling, capacity and number retention separately.
A number and an internet connection do not automatically replace every characteristic of an old line. Some legacy devices depend on functions that the new service may not reproduce. Get written confirmation from the equipment supplier rather than relying on the fact that an adapter has a familiar socket. Where replacement is needed, include installation and testing in the project schedule.
Check power and connectivity
Digital voice equipment generally depends on local power and a working connection. Ofcom’s guidance on moving landlines to digital technology explains why power cuts and connected devices need attention. Ask what backup arrangements apply to your service and how long any equipment is designed to operate under your actual conditions.
Test the agreed fallback in a controlled way. A mobile backup is useful only if it has suitable coverage, power and a functioning route when the primary service fails. If call diversion is configured on equipment inside the office, it may not run after that equipment loses power. Establish which part of the fallback is controlled by the provider and which part remains your responsibility.
Keep numbers and service changes coordinated
If you want to keep a published number, confirm the porting process with the receiving provider before ending the old service. Identify related broadband and other products that might be affected. A move should have an agreed order of operations, a contact for problems and a way to reach customers during disruption. Read the number-porting checklist for the necessary account information.
Do not use an order confirmation as the sole acceptance test. Make calls into the migrated number from relevant networks and check audio, menus, queues and voicemail. If outgoing service is included, confirm its operation and the provider’s emergency-calling arrangements using the appropriate agreed procedure. Do not make unarranged test calls to emergency services.
Close the project with evidence
Keep the device inventory, provider confirmations and test record together. Note any equipment that still needs attention and who owns the next action. Confirm which old services can be cancelled only after the dependent functions have been checked. Then review billing to make sure obsolete products have actually stopped and replacement charges match the agreed terms.
Finally, update the business continuity plan. Staff should know how calls are handled during an outage and where to find the escalation details. The aim is not merely to meet a headline date. It is to retain working communications and essential connected services through a change whose details depend on your own providers and equipment.